SUMMARY SHEET OF SIDING & PORT CONNECTIVITY PROPOSALS as on 13.5.2014

INDEX

S.No.

Siding/Industry

Pg No.

1

Cement

2,3

2

Power Plants

4,5

3

Iron & Steel

6

4

Coal/Washeries

7

5

Container

7

6

POL

7

7

PFT

8

Division

PFT

MUMBAI

2

NAGPUR

2

BHUSAWAL

SOLAPUR

PUNE

TOTAL

4

 

                 ACTIVE SIDING PROPOSALS

DIVISION

CEMENT

POWER PLANT

IRON & STEEL

COAL / WASHERY

CONTAINER

POL

TOTAL

MUMBAI

1

1

NAGPUR

2

6

3

3

1

1

16

BHUSAWAL

3

3

SOLAPUR

7

1

8

PUNE

1

1

TOTAL

10

10

4

3

1

1

29

    

                

Stage I –  ‘In-Principle’ approval (IPA) – Feasibility, Rail Transport Clearance

Stage II–  Approval of Engineering Scale Plan (ESP) & Detailed Project Report (DPR) in Division

Stage III-  Approval of Engineering Scale Plan & Detailed Project Report in HQ – Issue of Pucca No.

Stage IVLand Licensing, Interlocking Plan P, Bridge / Building Drawing, SWR/CRS, Estimates, Safety Certificate, ARN/Agreement.

I/W – Inward,  O/W - Outward

CEMENT

                                                                                                                                                                                                                                                                                                                                       NAGPUR DIVISION

Sr.No.

Name of  Siding

Take Off & section

Linkage

Lead Line

Cost

Rs. in Crores

Traffic Projection

Rakes/day

Commodity

Linkage

Current Status

Pending with

Remarks

1

M/s Reliance Cementation, Mukutban

(WR-BPQ section)

WCL

3 km

60.20

 I/W – 2 Coal

  O/W -1.5

Cement Clinker

IPA - 28.10.10.

HQ - CE(W)

Approvals to ESP/DPR sent to CE(W)  for issue of Pucca No. on 21.4.14.

Stage-III

2

M/s Reliance Cementation, Sindi

(NGP-WR section)

N.A.

I/W -1 Cement Clinker

O/W -1 Cement

IPA - 16.11.10.

Party

ESP/DPR to be submitted by party after completion of Mukutban Phase-I & II.

Stage-II

                                                                                                                                         SOLAPUR DIVISION

3

M/s LAFARGE SIDING, Wadi

(SUR-WD Section)

N.A.

I/W – 0.6

Coal, Fly Ash

O/W – 1.5

Cement

IPA - 28.1.11.

Divn

Party submitted  ESP/DPR in Divn. on 05.8.13. Party to comply Divn’s observations of 05.02.14.

Stage-II

4

M/s Gulbarga Cement Siding, Martur

(SUR-WD Section)

12 km

97.67

I/W – 1

Coal, Gypsum,Slag

O/W – 2

Cement, Clinker

IPA - 26.4.11.

Party

Pucca No. issued on 30.8.13.

Party to process further.

Stage-III

5

Vasavdatta Cement, Hotgi

(SUR-WD Section)

1 km

18.00

I/W – 3

Cement, Clinker

O/W – 2

Bagged Cement

Pucca No. - 16.1.12.

Party

Party to process further.

Stage-IV

6

Jaypee Cement Siding, Shahbad

(SUR-WD Section)

N.A.

I/W – 1

Coal, Gypsum

O/W-3

Cement

IPA - 21.11.11.

HQ – CE(W)

CE(W) to issue Pucca No. since 05.02.14.

 Stage-III

Sr.No.

Name of  Siding

Take Off & section

Linkage

Lead Line

Cost

Rs. in Crores

Traffic Projection

Rakes/day

Commodity

Linkage

Current Status

Pending with

Remarks

7

M/s Ultratech Cement Limited, Hotgi. Expansion Project.

(SUR-WD Section)

1 km

15.54

I/W- 2

Clinker, Gypsum

O/W – 2

Cement, Fly Ash

IPA - 30.1.12.

Party

Pucca No. issued on 18.01.13. Party to process further. Work nearing completion in ‘In-Plant’ area. Rly portion work yet to start.

Stage-IV

8

M/s Chettinad Cement Corpn., Tilati

(SUR-WD Section)

N.A.

I/W- 0.7 Clinker

O/W – 1 Cement

IPA - 03.9.12.

Party

Party to submit ESP/DPR in Divn. as per latest approved plan of Tilati station doubling.

Stage-I

9

M/s Zuari Cement Limited, Tilati

(SUR-WD Section)

N.A.

I/W – 1 Clinker

O/W – 0.5 Cement

IPA - 08.02.12.

Party

Party to revise and submit ESP/DPR in Divn on HQ’s suggestions since 22.4.14.

Stage-III

                                                                                                                                         PUNE DIVISION

10

Ultratech Cement Limited, Uruli

PA-DD end

3 km

28.48

I/W – 1 Bulk cement

O/W-NIL

IPA issued on 18.3.11.

Party applied for TDS on 31.3.11.

Sent to Rly Bd for approval on 20.6.11.

Party / Rly.Bd.

Rly Bd’s query and COM’s approval forwarded to Rly Bd on 23.01.12 for TDS. Pending with Rly.Bd.

Pucca No. issued on 22.4.14. Party to process further.

Stage-IV


POWER PLANT

NAGPUR IVISION :

   

Sr.No.

Name of  Siding

Take Off & section

Linkage

Lead Line

Cost

Rs. in Crores

Traffic Projection

Rakes/day

Commodity

Current Status

Pending with

Remarks

11

M/s Vidarbha Industries Power Limited (VIPL) siding, Sindi

Power Plant- 300MW

(NGP-WR section)

WCL

17 km

200.52

I/W – 2 (Coal)

O/W – NIL

Pucca no. issued on 03.6.11.

Party

Siding work in progress.

Stage - IV

12

M/s EMCO Energy Limited, Chikni Road

Power Plant- 2x135 MW

SECL

6 km

49.33

I/W – 1.5 (Coal)

O/W – NIL

Pucca No. issued on 03.02.11.

Party

Siding commissioned on 29.5.13.

Phase-II in progress.

TD not advised by Party.

Stage – IV

13

M/s Chandrapur Super Thermal Power Station(CSTPS),  Chandrapur

2340 MW Plant

Expansion of Power Plant

2x 500 MW(WR-BPQ section)

WCL, SECL

6 km

153.10

Existing- I/W - 8

Proposed – I/W -6

Coal

O/W - NIL

Phase-I work completed on 12.5.11.

Pucca No. -28.5.12 for Phase-II.

Party

Siding expansion Phase-II work in progress.

TD – Mar.’14. Revised TD not advised.

Stage –IV

14

Satpura Thermal Power Station, (STPS) Sarni

Augmentation of Thermal Power Station (1142.5 MW to 1642.5 MW) (ET-NGP section)

SECL

17 km

66.75

Existing-I/W-4 Proposed-I/W-7

Coal

O/W – NIL

Pucca No. -05.01.12.

Party

Siding expansion work in progress.

TD not advised by Party.

Stage-IV

15

Wardha Power Company Limited, Warora, 540+300 MW

(WR-BPQ Section)

WCL

5 km

29.00

I/W – 1.5 Coal

O/W - NIL

Phase – I completed. ARN issued on 12.01.11.

Party

Phase-II work in progress.

TD – May’14.

Stage-IV

Sr.No.

Name of  Siding

Take Off & section

Linkage

Lead Line

Cost

Rs. in Crores

Traffic Projection

Rakes/day

Commodity

Current Status

Pending with

Remarks

16

Gupta Energy Pvt. Ltd.,  Ghugus, 660 MW

(TAE-GGS Section)

N.A.

I/W – 3.0 Coal

O/W - NIL

IPA - 30.4.13.

Party

Party to submit ESP/DPR in Divn.

Stage-II

BHUSAWAL DIVISIN :              

17

Indiabulls Power Co. Ltd., Walgaon (on new B.G.Line)

1350 MW capacity

SECL WCL

24 km

173.96

I/W – 4

Coal

O/W - NIL

Phase-I

Pucca No. issued on 6.1.11.

Temp unldg facility at Walgaon –I

Walgaon - II

Party

Siding work in progress.

TD – July’14.

Stage – IV

- Commissioned on 20.6.13.

- Conceptual plan for temporary unloading Walgaon-II feasibility sent to Divn on 17.02.14.

18

Indiabulls Power Limited, Sinnar SEZ, Nasik

SECL WCL

29 km

225.98

I/W – 4

Coal

O/W - NIL

IPA given on 03.12.10.

Temp unldg facility

AT MAHAGENCO

IPA given on 01.6.12.

Party

Party

Pucca No. issued on 09.10.13.

Party to process further.

Stage-IV

Party to obtain NOC from MAHAGENCO.

19

MSPGCL, Paras

Expansion project of 2x250 MW

Mhajanwadi Coal Block

1 km

N.A.

I/W – 2.0

Coal

O/W – NIL

IPA-16.01.14

Party

Party to submit ESP/DPR in Divn.

Stage - II

                                                                                                           SOLAPUR DIVISION :

20

NTPC, Hotgi

(SUR-WD Section)

Mahanadi  Coal Fields (CIL)

207.00

I/W – 5

Coal

IPA - 05.10.10.

Party

Pucca No. issued on 22.11.13.

Party to process further.

Stage -III

IRON & STEEL

                                                                                                                                       MUMBAI DIVISION

Sr.No.

Name of  Siding

Take Off & section

Linkage

Lead Line

Cost

Rs. in Crores

Traffic Projection

Rakes/day

Commodity

Current Status

Pending with

Remarks

21

Ispat Industries Limited

Dolvi, (Pen-Thal section)

5 km

20.00

I/W – 1.5 Iron Ore

O/W-1 Hot rolled coils

Siding commissioned on 21.6.13.

Party

Divn

Party to complete balance work of Phase-II. Interlocking work pending.

Stage-IV

Party applied for additional facilities inside siding. Conceptual Plan/FSR submitted on 31.12.13 in Divn. Divn to offer remarks.

                                                                                                                            

NAGPUR DIVISION

22

Grace Industries Limited, 4x100 TPD DRI Klins with a 33 MW captive Power Plant in MIDC, Tadali, (WR-BPQ)

2 km

27.90

I/W – 1.2 (Coal & Iron Ore)

O/W - NIL

IPA given on 06.12.12.

Party

ESP/DPR appd by Divn. circulated in HQ on 30.01.14. Party to comply HQ’s observations.

Stage-III

23

Chandrapur Ferro Alloys, Chandrapur (WR-BPQ) expansion Plan

N.A.

I/W – 0.5 (Coke Coal, Iron ingots)

O/W – 0.5 (Steel Products)

IPA given on 02.4.13.

Party

Party to submit ESP/DPR in Divn.

Stage-II

24

Uttam Galva Metallics Limited, Chitoda, Wardha

(WR-BPQ)

1 km

N.A.

I/W – 3.0 (Iron Ore, Dolomite,Coal)

O/W – 1.5 (HR Coils, Galvanized sheets)

HQ’s observations sent to Party.

Party

Party to comply HQ’s observations of 23.4.14.

Stage-I

                                                                                                                                                                                                                                                                                                                                                   

COAL / WASHERY

NAGPUR DIVISION

Sr.No.

Name of  Siding

Take Off & section

Linkage

Lead Line

Cost

Rs. in Crores

Traffic Projection

Rakes/day

Commodity

Current Status

Pending with

Remarks

25

KEMTA, Majri

(WR-BPQ Section)

2 km

15.93

Coal Loading

I/W –  NIL

O/W - 1.5 Coal

DOA – 10.3.12

For Augmentation work

HQ

Party intimated deposit of complete amount on 09.4.14 for balance work. Proposal under scrutiny in HQ.

Stage-I

26

Jaiprakash Associates, Khirsadoh

(AMF-CWA section)

1 km

23.97

Coal Loading

I/W –  NIL

O/W - 1.5 Coal

DOA – 20.11.13

Party

Party to comply of HQ’s observations of 09.5.14.

Stage-I

27

WCL, Umrer

(Butibori-Umrer sectin)

1 km

5.71

Coal Loading

I/W – NIL

O/W – 1.5 Coal

IPA – 23.5.13

CE(W) - HQ

Approvals to ESP/DPR sent to CE(W)  for issue of Pucca No. on 23.4.14.

Stage-III

                                                                                                  

                                                                                              

CONTAINER

NAGPUR DIVSION

28

M/s ETA

Integrated Plan, Borkhedi

(NGP-WR section)

1 km

19.60

I/W – 0.5

O/W – 0.5

Container

IPA given on 20.9.10.

Party

Revised ESP/DPR under HQ approval since 23.5.13. Party to comply on CCM’s observations of 10.10.13.

Stage-III     

POL

NAGPUR DIVSION

29

M/s HPCL LPG, Khapri

Expansion Plan

(NGP-WR section)

1 km

1.97

I/W – 0.16

LPG rakes

Divn to offer remarks on feasibility

Party

Party to comply on Divn’s observations of 04.4.14 on the Conceptual plan and Pre-FSR.






PFT

 BB Divn.

.

S.N

Name

Traffic Projections

Date of Initial Application

Date of complete submission  of Documents

Date of Screening by SAG Committee

Date of ‘In-Principle’ approval

Date of submission  (i) DPR

(ii) Engg/Bridge drawing

Approvals / Pending with

Completion of work (within 1 year of all approvals)

Remarks

1

Tata Steel Limited

Kalamboli

(Diva-Panvel section)

Bagged commodities

Containers

1 km

25.01.11

03.08.11

16.9.11

21.11.11

27.12.11

(Submitted in Divn)

Pucca No. issued on 10.02.14.

Party to process further.

2

M/s  PNP Maritime Services, Pvt. Ltd., Dharamtar (Pen-Thal Section)

19.81 Cr

1 km

18.01.12

10.4.12

Not Reqd

WIP by Party

IPA is held up for completion of balance work of Interlocking & Stn. Bldg. by Party.

TD not advised by party.

         

NGP Divn.                                                                                                                                                  

3

M/s BOXTRANS Logistics, Borkhedi (NGP-WR section), Greenfield

1 km

18.7.13

Party

Party to comply on HQ’s observations of 11.4.14 on Conceptual plan.

4

M/s CONCOR, Khapri (NGP-WR sectiom)

Greenfield

1 km

13.11.13

HQ

Party complied on HQ’s observations on conceptual plan. Under scrutiny in HQ since 23.4.14.


 PFT commissioned

                        Private Freight Terminal  commissioned since 2008

S.No.

Private Freight Terminal

Status

1

M/s Lloyds steel ltd, Wardha, Nagpur

Commissioned in 2011

2.

M/s Navkar Corporation Ltd. Somatne, Mumbai

Commissioned in 2012

3

M/s Vimla Infrastructure Ltd. Tadali, Nagpur.

Commissioned in 2012
















Source : Central Railway / Indian Railways Portal CMS Team Last Reviewed on: 09-06-2014  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.