1. GENERAL INFORMATION OF ENGINEERING DEPARTMENT
1.1 BRIEF HISTORY OF SOLAPUR DIVISION
1.1.1 SOLAPUR DIVISION PRESENTLY CONSIST OF:
Route Kilometers:B.G.728.525 Km
Track Kilometers: B.G. 1071.46 Km.
1.1.2 HERITAGE:
a) G.I.P. Railways : Pune to Gangapur Rd
b) Nizam State Railways : Gangapur Road to Wadi
c) Barsi Light Railways : Miraj-Kurduwadi-Latur
1.1.3 MILESTONES:
|
a) |
1858-1870 |
: |
Pune-Wadi Main Line was constructed. |
|
b) |
1878 |
: |
Daund-Manmad Main Line was constructed. |
|
c) |
1906-1911 |
: |
Barsi Light Railway was constructed. |
|
d) |
1914 |
: |
Daund-Baramati N.G.Line was constructed. |
|
e) |
1970 |
: |
Pune-Daund section was doubled. |
|
f) |
1970 |
: |
SDB-WD Section was doubled. |
|
g) |
1988-1989 |
: |
Shahabad-Gulbarga section was doubled. |
|
h) |
1994 |
: |
Daund-Baramati Line was converted into B.G. |
|
i) |
1999 |
: |
Solapur-Hotgi section was doubled in 1997-1999. |
|
j) |
2001 |
: |
Kurduwadi- Pandharpur Line was converted into BG. |
|
k) |
2002 |
: |
Daund - Bhigwan section was doubled in 2002. |
|
l) |
2003 |
: |
Latur - Latur Road New BG Section commissioned in Dec- 2003 |
|
m) |
2007 |
: |
Latur - Osmanabad Gauge Conversion section commissioned in Aug -2007. |
|
n) |
2007 |
: |
Solapur –Pakni section was doubled in Aug -2007. |
|
o) |
2008 |
: |
Pakni-Mohol section was doubled in May -2008. |
|
p) |
2008 |
: |
Osmanabad-Kurduwadi Gauge Conversion section commissioned in June - 2008. |
|
q) |
2009 |
: |
PB-ShirdiNew line ( 17 kms) commissioned on 20.02.2009 |
|
r) |
2011 |
: |
PVR-MRJ Gauge conversion opened for passenger traffic in Feb. 2011. |
|
s) |
2015 |
: |
HG-BJP Line 0.877 kms icmseased to SUR Divn. from SWR Zone. |
|
t) |
2015 |
: |
HG-TLT UP line 6.45 kms commissioned on 15.03.2016. |
|
u) |
2016 |
: |
MO-WKA UP line 22.49 kms commissioned on 05.02.2017. |
|
v) |
2017 |
: |
ANG - Narayandoh New line (12.275 kms) commissioned on 29.03.2017 |
|
w) |
2017 |
: |
TLT - AKOR UP line13.88 kms commissioned on 03.04.2017 |
|
x) |
2017 |
: |
GR-Sultanpur New line 11.90 kms commissioned on 29.10.2017 |
|
y) |
2017 |
: |
WKA-WDS UP line 14.98 kms commissioned on 19.03.2018. |
|
z) |
2018 |
: |
AKOR-NGS UP line 5.12 kms commissioned on 27.05.2018 |
|
aa) |
2018 |
: |
NGS-BOT UPline 8.98 kms commissioned on 05.10.2018 |
|
ab) |
2018 |
: |
NODH-SRWD new line 23.265 kms commissioned on 23.03.2019 |
|
ac) |
2019 |
: |
WDS-BLNI Up line 34.72 kms commissioned on 22.08.2019 |
|
ad) |
2019 |
: |
PA-DD-MMR chord line 1.258 kms commissioned on 19.09.2019 |
|
ae) |
2019 |
: |
KPG- YL Up line 13.613 kms commissioned on 04.10.2019 |
|
af) |
2019 |
: |
KLBG- SVG Up line 13 kms commissioned on 26.11.2019 |
|
ag) |
2020 |
: |
BOT-KUI Up line 23.49 kms commissioned on 25.02.2020 |
|
ah) |
2020 |
: |
HG-BJP Up line 2.555 kms commissioned on 10.08.2020 |
|
ai) |
2020 |
: |
YL- ANK Up line 15.13 kms total & 14.55 of SUR division Commissioned on 14.09.2020 |
|
aj) |
2020 |
: |
KUI-SVG Up line 26.99 kms commissioned on 12.11.2020 |
|
ak) |
2021 |
: |
BLNI-WSB 26.33kms Up line commissioned on 27.10.2021 |
|
al) |
2021 |
: |
Solapurwadi - Ashti 30.649 kms new line commissioned on 31.12.2021 |
|
am |
2022 |
: |
Bhigvan (BGVN)- Washimbe (WSB) 28.48 kms Up line commissioned on 09.08.2022 |
|
an |
2022 |
: |
KSTH-BWD 24.88 kms Up line Commissioned on 19.10.2022 |
|
ao |
2023 |
: |
Kanhegaon-Puntamba 15.27 Kms Commissioned on28.01.2023 |
|
ap |
2023 |
: |
Belapur-Puntamba 19.98 Kms Commissioned on29.03.2023 |
|
aq |
2023 |
: |
Belapur- PDGN 12.42 Kms Commissioned on22.07.2023. |
|
ar |
2023 |
: |
SRL-AKR 5.77 Kms Commissioned on25.09.2023 |
|
as |
2023 |
: |
BWD-VPR 14.03 Kms Commissioned on 09.11.2023 |
|
at |
2024 |
: |
New Ashti- Amalner 32.84 Commissioned on05.01.2024 |