Electrical General Services Organization is headed by Senior Divisional Electrical Engineer (G) who is assisted by Assistant Divisional Electrical Engineer (G) along with Sr.Section Engineers and Junior Engineers. Organization is divided into OSM & ETL groups.
OSM group looks after the repairs and maintenance of Distribution substations, LT & HT overhead lines, Electrical pump sets, DG sets, Lifts, Escalators, Water coolers, RAC equipment, etc. Major Depots handling this work in the sections of Bhusaval Division are as below.
|
Depot |
Headed by |
|
Manmad Depot |
Sr. Section Engineer (E/M), Manmad |
|
Bhusaval Depot |
Sr. Section Engineer (E/M), Bhusaval |
|
Akola Depot |
Sr. Section Engineer (E/M), Akola |
|
Chalisgaon Depot |
Sr. Section Engineer (E/M), Chalisgaon |
|
Khandwa Depot |
Sr. Section Engineer (E/M), Khandwa |
ETL group looks after the maintenance of primary and secondary rakes, AC coaches, sectional coaches etc. It is also responsible for attention of passing trains in case of complaints regarding TL equipment. Major Depots handling this work in the sections of Bhusaval Division are as below.
|
Depot |
Headed by |
|
Manmad Depot |
Sr. Section Engineer (TL), Manmad |
|
Bhusaval Depot |
Sr. Section Engineer (TL), Bhusaval |
|
Amravati Depot |
Sr. Section Engineer (TL), Amravati |
Brief History
Bhusaval station is the first electrified station of the Division, electrified in the Year 1931. Earlier there was Railways Thermal Power House at Bhusaval maintained by Elect (G) branch to cater the demand of Electricity required for Railways installation like station lighting, pumping, etc. There after phase wise other stations were electrified. At present Electricity is purchased from SEB’s for all 95 Electrified stations, Level crossing Gates, etc. Electrical (G) branch looks after all Electrical works other than Traction.
Major Assets
OSM
|
Assets |
Qty (No’s) |
|
Electrified Stations |
095 |
|
Staff Quarters Electrified |
6032 |
|
Water Coolers |
262 |
|
HT supply points |
21 (19 MSEDCL & 2 MPPKVVC L) |
|
LT supply points |
284 |
|
Substations |
55 |
|
Transformers |
115 |
|
Electrical Pump sets |
305 |
|
Stationary DG sets Higher Capacity |
58 |
|
Solar water heaters |
43 |
|
Electrified LC Gates |
55 |
|
Solar standalone street lights |
337 |
|
Passenger Lifts on stations |
45 |
|
Escalators |
21 |
|
Grid connected Solar Rooftop Plants |
61 |
ETL Assets Qty (No’s) TL Coaches 29 LHB AC Coaches 35 LHB non AC Coaches 46 Power Car 06 Memu 136
1.Illumination standard of stations improved.
2.100% LED lighting on all Stations & Service Buildings.
3.Installed 3580 KWp capacity Solar PV Plants in Division.
4. Total 79 Nos. solar hut of 2 KWp, 3 KWp and 4 KWp capacity are provided at various stations.
5.Solar tree provided in BSL south side circulating area for beautification.
6.21 No’s Escalators & 45 No’s Lifts provided on major stations.
7.Tri-lingual Digital signages provided at major stations.
8.USB mobile chargers provided at major stations.
9.Provided Air conditioning for Waiting Rooms at Burhanpur, Akola, Nashik Road & Bhusaval stations.
10.Provided Monumental flags at 18 stations.
11.Provided HVLS ceiling fans at major stations.
12.LED name boards provided at major stations.
13.Panchvati & Amravati Express running with comfortable LHB coaches. HOG is used for this train which is most economical and safe.
14.EPIS provided in coaches of AMI-CSMT Express with display and audio for information of passengers. Welcome message, Date, Time, Originating station, Destination, Next Halt station, Distance, etc. is displayed.
15. BLDC fans provided in place of higher wattage fans.
16. Prepaid meters installed in place of conventional meters.

Accessibility Controls