Achievements of ACCOUNTS OFFICE, MUMBAI DIVISION for the month of MAY 2022 is as under:-

 

A)      Finance Section:-      

Due to thorough scrutiny of financial Proposals, Indents & Estimates, savings to the tune of Rs. 6.99 crores have been achieved. 

Ř  Major Savings:

Ř  Savings of Rs.1.36 crores achieved, the abstract estimate for the work ‘Provision of BPAC in left over 21 block sections in Mumbai Division’ was sanctioned on IRPSM for Rs. 6,98,82,089.59 chargable to RRSK.

But the detailed estimate was prepared by the Department amounting to Rs. 8,34,28,357.53. This office returned the detailed estimate since this was a work sanctioned as Umbrella work and as per extant rules, no excess

 over sanctioned cost is permissible for umbrella works. The Department therefore revised the detailed estimate to 6,98,75,735.06 by reducing number of block sections to be covered under this work.

 

B)      Bills Recoverable Section:- The following major amount recovered against Bills raised: 

Sr. No

Party Name

Bill Type

Amount (Rs. In Lakhs)

1

CONCOR

Land Licence

126.74

2

Cotton Corp. Of India

Land Licence

78.99

3

JSW

Land Licence

128.39

4

ADANI Ports & Logistics

Land Licence

71.78

5

Navkar Corp. Ltd

Land Licence

294.84

5

Navkar Corp Ltd

Interest & Maintenance

13.15

 

C)      Revenue and Capital Expenditure :-Working Expenses (Demand 03 to 13):

                                                                                                                                                               (Rs. in. Crs.)

Revenue D. No.    3 to 13

Expenditure for the month of

April 2021

Expenditure to end of

April 2022

 

Actual  April 21

Actual April 22

Variation (%)

Actual  April 21

Actual April 22

Variation (%)

 

297.58

407.40

36.90

297.58

407.4

36.90

Works (Exp.)

21.20

37.23

75.61

21.20

37.23

75.61

   

D)        Bill passed and amount for the month of May 2022. 

 

SECTION

NO. OF BILL PASSED

AMOUNT IN CR.

EXP

353

99.01

Stores Bills

241

3.32

Petty Bills

1216

9.75

E)      Achievements:

Ř  Expenditure Section:-                 An amount of Rs. 26.46 Lakh has been recovered from ON Account Bills of contractors during the month of May 2022 on account of deduction of penalty, bill charges, vetting charges etc.

Ř  Establishment Section:- This office has discussed the matter with all concerned departments such as Personnel, EDP & Operating and arranged a meeting for the implementation of CMS with IPAS in which necessary

decisions were made and the same are materialised successfully to implement the integration of Crew Management System with IPAS.

Thus this office had taken a lead in implementation of CMS with IPAS in Mumbai Division and would ensure continuous improvement with coordination of all concerned departments.

Assistance Required from HQ:-

·         As against 9 sanctioned posts of ASVs only two posts of ASV are being operated. Vacancies of ASVs (7 posts) required to be filled up urgently for stock verification and witnessing of scarp sale.

& Pay sheet section (4).