Infrastructure Upgrade - Jalgaon-Bhusaval 4th line |
 Infrastructure Upgrade - Jalgaon-Bhusaval 4th line Central Railway, continuing its strides towards infrastructure upgradation, carried out launching of 30.5-meter span open web girder weighing 100 MT of Rail Fly Over on Bhadli-Jalgaon 4th line (part of Jalgaon-Bhusaval 24km - 4th line project) on 12.1.2022.The main girder was launched by end-launching method with launching nose of 21-meter span attached to the main girder. 5 temporary support trestles were erected for movement of girder assembly. The track over the girder is pre-linked with H-beam sleepers. The launching of the girder completed by operating 4 hours block on the section.--- ---Date: January 18, 2022PR No.2022/01/29This press release is issued by the Public Relations Department, Central Railway, Chhatrapati Shivaji Maharaj Terminus Mumbai.
(Shivaji Sutar) Chief Public Relations Officer
|
|
|
|
|