Current Status of Kalyan Yard Remodelling work is as under:
The project is aimed at Construction of 4 new Coaching platforms in Kalyan goods Yard for segregation of Mail/Express and Suburban local trains’ traffic.
Contract for “Earthwork, Minor Bridges & Miscellaneous Civil Works” has been awarded. Works of Drain & Boundary wall, Earthwork in formation work for Phase one for Goods line is in progress. Approx. 50% of work is completed.
Contract for “Relocation of Affected Service Buildings & Quarters” has been awarded. Construction work of service buildings which are coming in the alignment of proposed track in progress. Out of 10 service buildings, works of 8 buildings are in progress in which foundations work in 8 buildings are completed.
Contract for track related works has been awarded. Dismantling is in progress and approx. 90 % of dismantling completed.
After Kalyan Yard inspection Shri Naresh Lalwani inspected Kalyan AC Electric Loco Shed, Kalyan.
--- ---- --- ---