Important infrastructure works on 23 FOB locations on CR since lockdown

Central Railway

Press Release

Important infrastructure works o­n 23 FOB locations o­n CR since lockdown

Ever since the lockdown was announced in last week of March 2020, in addition to running freight trains for keeping essential supplies without break and running select special passenger trains across India, Central Railway has completed important infrastructure work utilising the lockdown period. The amount of work it has done would have required many traffic blocks and impact o­n some trains running during normal period. Infrastructure work at 23 locations over Central Railway for launching of steel girders for 14 Foot Over Bridges and dismantling distressed steel structures of 9 Foot Over Bridges were carried out since lockdown.

Out of these 23 important infrastructures works, 7 were o­n Mumbai Division, 10 in Bhusaval Division, o­ne each in Nagpur and Solapur Divisions, 3 o­n Pune Division and o­ne by Construction wing.The details are as under:

Mumbai Division:

·Launch of girders for 6 meter wide foot over bridge (FOB) at Dombivali station and 3.66 meter wide midsection FOB near Belapur station.

·Dismantling of distressed steel 2 spans of FOB at Vadala Road, o­ne span of FOB at Ambarnath, o­ne span of FOB at Ambivli, 2 spans of FOB at Atgaon.

·Dismantling of two spans of more than 100-year-old FOB at Vasind railway station.

Nagpur Division:

·Launching of 6 meter wide FOB girders having 6 spans crossing 16 Railway tracks at Wardha station

 

Bhusaval Division:

·Girdres launching for replacement of old FOB with a new 4.88 metre FOB at Bhusaval station

·Launching of girders of 3.66 metre wide FOB at Bodwad station o­n Bhusaval-Badnera section and o­ne FOB at New Amravati in Badnera-Narkher section.

·Launching of girdersfor replacement of old FOB by 6 metre wide FoB at Akola station

·Launching of girders for 3.66 metre wide FoBs at Chandur Bazar station and Amravati station o­n Badnera-Narkher section and o­ne at Nandura station o­n Bhusaval-Badnera section

·Dismantling of old corrugated steel structures of distressed FOBs at Bhusaval, Nashik Road and Shegaon stations

 

Solapur Division:

·Launching of girders of 6 meter wide FOB at Daund station

 

Pune Division:

·Launching of girders for 3.66 metre wide FoB at Kadethan station, 6 meter wide FOB at Chinchwad station

·Dismantling of 2 spans of FOB at Talegaon station

 

Construction wing:

·Construction of 3 metre wide FOB at Bhavaninagar station o­n Pune Division

 

Optimum utilisation of manpower due to lockdown, effective utilisation of limited resources and machinery and duly observing norms mandated for COVID19 were observed during execution of above works.

---- ----

Date: July 15, 2020

PR No.2020/07/22

This press release is issued by the Public Relations Department, Central Railway, Chhatrapati Shivaji Maharaj Terminus Mumbai






  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.