Dadar Terminating/Originating Trains will be extended to run upto Parel and will originate from Parel due to infrastructure work of widening of Dadar platform no. 1 width from 15.09.2023 onwards*
In order to facilitate crowd for a better crowd management, it is decided to widen platform width of Dadar platform no. 1. At present length of Dadar platform no. 1 is 270 mtr and width is 7 meter. It is decided to increase width from current 7 meter to 10.5 meter. Thus width increase will be by 3.5 meter additional. The work will start from 15.09.2023 (Friday), it is expected to complete the work in coming 2 months with the cost of 1 crores.
Widening of width will facilitate increasing width of FOB (Foot Over Bridge) staircase also after completion of work of platform no 1 width widening, and it will also facilitate provision of new escalators on platform no 1.
At present, Dadar platform no. 1 / 2 have total 2 FOB (Foot Over Bridge). For this width widening works, all slow locals (Up + Dn) which originates/terminates from Dadar platform no. 2 are hereby extended upto Parel suburban terminus. Thus following 11 pairs of Dadar originating/terminating slow locals will henceforth originate/terminate from Parel station from 15.09.2023 (Friday) to till further advice.
Due to Widening of PF No 1 at Dadar & Closing of Dadar PF No 2, following Dadar terminating services will be extended up to Parel & Dadar originating services will be originated Ex Parel w.e.f. 15.09.2023 (Friday) till further advice to facilitate the work of widening of Dadar PF 1 & Closing of Dadar PF 2. The details of the 11 pairs suburban services which are to be extended are as under:-
• Thane-Dadar arriving Dadar at 08.07 hrs will run upto Parel arriving at 08.13 hrs and will depart Parel at 08.17 hrs for Kalyan
• Titwala-Dadar arriving Dadar at 09.37 hrs will run upto Parel arriving at 09.40 hrs and will depart Parel at 09.42 hrs for Kalyan
• Kalyan-Dadar arriving Dadar at 12.55 hrs will run upto Parel arriving at 12.58 hrs and will depart Parel at 13.01 hrs for Kalyan
• Thane-Dadar arriving Dadar at 17.51 hrs will run upto Parel arriving at 17.54 hrs and will depart Parel at 17.56 hrs for Dombivali
• Thane-Dadar arriving Dadar at 18.10 hrs will run upto Parel arriving at 18.13 hrs and will depart Parel at 18.15 hrs for Kalyan
• Dombivali-Dadar arriving Dadar at 18.35 hrs will run upto Parel arriving at 18.38 hrs and will depart Parel at 18.40 hrs for Kalyan
• Thane-Dadar arriving Dadar at 19.03 hrs will run upto Parel arriving at 19.06 hrs and will depart Parel at 19.08 hrs for Kalyan
• Dombivali-Dadar arriving Dadar at 19.39 hrs will run upto Parel arriving at 19.42 hrs and will depart Parel at 19.44 hrs for Dombivali
• Thane-Dadar arriving Dadar at 19.49 hrs will run upto Parel arriving at 19.52 hrs and will depart Parel at 19.54 hrs for Thane
• Kalyan-Dadar arriving Dadar at 20.20 hrs will run upto Parel arriving at 20.23 hrs and will depart Parel at 20.25 hrs for Kalyan
• Thane-Dadar arriving Dadar at 22.20 hrs will run upto Parel arriving at 22.23 hrs and will depart Parel at 22.25 hrs for Thane
All concerned to please note. Passengers are requested to bear with the Railway Administration for the inconvenience caused.
THESE INFRASTRUCTURE UPGRADE WORKS ARE FOR A BETTER TOMORROW.
--- --- --- --- --- --- ---
Date: September 12, 2023