Opening of new Private Sidings / Private Freight Terminals
|
Updated Upto Oct 2023 Sr No. | Subject | | | 1 | Time line For Private Sidings Projects | | | No. | Service | Time limit | Single Window Agency (to be contacted for progress/ non-compliance) | 1.2 | Signing of Siding agreement | 5 days | Sr.DCM of concerned Division | (working days from the date of completion of work) | Mumbai division | | srdcm@bb.railnet.gov.in | | Pune division | | srdcm@pune.railnet.gov.in | | Bhusawal division | | srdcm@bsl.railnet.gov.in | | Nagpur division | | srdcm@ngp.railnet.gov.in | | Solapur division | | srdcm@ngp.railnet.gov.in | 1.3 | Notification after certification | 05 days | | (after receipt of completion certificate and signing of Siding Agreement and Land Licensing Agreement | |
Source : Central Railway / Indian Railways Portal CMS Team Last Reviewed : 16-11-2023
|
|
|