ORGANISATION :- Electric Loco Shed, Bhusawal (TRS)
ORGANIZATION :-
(A)GAZZETED :
Traction Rolling Stock (TRS) Electrical branch of the division is preceded by Senior Divisional Electrical Engineer (TRS) Bhusawal. He is assisted by DEE(TRS) & ADEE (TRS).
(B)NON GAZZETED :
Sr.No. | Category | Sanction Strength | Men on Roll | Vacancy |
1. | Supervisors | 80 | 73 | 07 |
2. | Artisans | 498 | 496 | 02 |
3. | Un-skilled | 112 | 78 | 34 |
4. | Ministerial & Other Staff | 46 | 31 | 15 |
| Total | 736 | 678 | 58 |
History and Activities
Electric Loco Shed Bhusaval is one of the pioneer maintenance shed on Indian Railways, situated on Mumbai - Howrah & Mumbai - Delhi main line and came in to existence in the year 1968. The shed was originally designed for a holding capacity of 55 engines. ELS/BSL were maintained various types of locos such as WAG-2, WAG-4, WAG-7, WAM-4, locos in past period. At present WAG-5 WAP-4 & WAG-9H locos are maintained by shed. Electrical Loco Shed, Bhusawal has been accredited with International Standard Certificate ISO 9008-2000 since April 2006 and International Standard Certificate ISO 9001: 2008, ISO 14001: 2004, OHSAS 18001: 2007 since September 2016. Electrical loco shed, Bhusawal has done many important activities with loco maintenance which will serve as mile stones in the history of Indian Railways.
From 2018, Three phase locos maintenance started in shed. At present 33 Nos. WAG-9H loco in holding.
ELS/BSL has been converted 03 Nos. battery operated dual mode shunting loco from condemned WAG-5 which can work in unwired section dispensing with the necessity of Diesel Loco for yard shunting.
Shed is performing following activities
Minor Schedule : IA, IB, IC
Major Schedule : AOH, IOH
Holding
S.N. | Loco Type | Holding |
1 | WAG-5 | 118 |
2 | WAP-4 | 71 |
3 | WAG-9H | 33 |
| Total | 222 |
LOCO HOLDING
Loco Capacity – 175
Current Loco Holding - 222
Goods (WAG 5 & WAG-9H) -151
Passenger ( WAP-4) -71
PERFORMANCE
S.N. | Parameter | Up to End of the Month Aug. |
2022-23 (%) | 2023-24 (%) |
1 | Asset failure/100 Loco* | 35.31 | 27.70 |
2 | KM/Asset Failure (in Lakh) | 2.42 | 3.45 |
3. | Statistical Ineffective Percentage | 8.66 | 6.94 |
4 | Outage (%) | | |
a) | Coaching | 86.65 | 92.86 |
b) | Goods | 91.24 | 91.87 |
c) | Total | 90.21 | 92.2 |
5 | AOH & IOH | 39 | 39 |
6 | Un-schedule Lifting/100 Loco | 27.00 | 23.24 |
7 | Un-schedule Visit/100 Loco | 6.75 | 8.04 |