1. | Kurla ? Thane 5th & 6th line completed and preparation for CRS inspection carried out except yard remodeling at Vidyavihar, which is in progress. |
2. | Yard remodeling works at Panvel was commissioned on 19.4.10. This will now enable to run more services between Thane- Panvel and Vashi ? Panvel section. |
3. | Work of Extension of PFs for running of 12 car rakes in Thane-Vashi-Panvel section has been completed for all 12 stations. |
4. | 6 Nos. of stabling siding has been commissioned at Vangani on 05.09.2010. Also 1024 Port Data logger & 12 nos. AFTCs are commissioned at Vangani. |
5. | Cover over Mulund goods shed completed on 10.11.10. |
6. | 2.44 m FOB at Puntamba on all 4 tracks completed on 16.09.10. |
7. | Washable aprons at Amravati on platform No. 2 & 3 completed in May 10. |
8. | New landing from Masjid ROB to Harbour line platform at Masjid station has been commissioned.This has given great relief to commuters. |
9. | Following Electrical works have been completed: (i)Transformer of capacity 21.6 MVA at Multai commissioned on 23.07.10 and that at Betul commissioned on 23.11.10. (ii)DRPC at Nashik Road has been commissioned on 14.08.2010. (iii)Chalisgaon DRPC capacitor bank commissioned on 21.09.10. (iv)Transformer 21.6 MVA at Pachora charged on 14.12.10. |
10. | Survey work of Narkher-Badnera extension of new BG line upto Washim completed on 18/6/10. |