1. SPECIAL IMPROVEMENT / ACHIEVEMENT:
1.1 All Unmanned LC eliminated by 31.03.2015
1.2 Nos. of manned LC closed during 2021-22= 11 Nos.
1.3 Nos. of Rehabilitation Bridges during 2021-22 =17 Nos.
1.4 Removal of Permanent speed Restriction during 2021-22 = 3 Nos.
1.5 Track Rail Renewal during 2021-22 = 51.594 Kms.
1.6 Total 26.33 km doubling work completed in FY 2021-22. (BLNI-WSB 26.33 km), 30.649 km New line completed in FY 2021-22.(Solapurwadi-Asthi 30.649 km)
2. ENVIRONMENT RELATED WORK:
Position of STP (Sewage Treatment Plant), Auto–Chlorination plant on Solapur Division
2.1. Provision of STP (Sewage Treatment Plant)-There are three nos. of STP plant
are commissioned as below:
· LUR -15KLD capacity-plant commissioned on 19.07.2020.
2.2. STP (Sewage Treatment Plant)-Presently, Five nos. of STP plant of capacity of 15/50
KLD are being executed:
· ANG - 50KLD capacity- Work is in progress.
· KPG – 15KLD capacity- Work is in progress.
· SNSI – 15KLD capacity- Work is in progress.
· SUR- 15KLD capacity- is being commissioned shortly.
· The recycled water is being utilized for PF, Apron & Carriage washing. Also this water is being utilized for maintenance of gardens
3. Auto–Chlorination plant –
There are total 80 nos of Auto –Chlorination plant are provided on various location/stations of division for improvement to quality of drinking water.
4. CRS INSPECTION:
4.1. CRS inspection of Yeola–Ankai section doubling (15.13 km total & 14.55 of SUR division) done on 14.09.2020 CRS vide authorization letter No. C-12(230)/2020/456 dtd. 14.09.2020 accorded sanction for opening Yeola-Ankai newly constructed B.G. line for doubling for the public carriage of passengers at max. permissible speed of 100 kmph.
4.2. CRS inspection of Savalgi–Kulali section doubling (26.99km) done on 11.11.2020 CRS vide authorization letter No. C-12(234)/2020/573 dtd. 12.11.2020 accorded sanction for opening Savalgi – Kulali newly constructed B.G. line for doubling for the public carriage of passengers at max. permissible speed of 90 kmph.
5. IMPROVEMENTS IN PASSENGER AMENITIES:
5.1. At Sainagar Shirdi - Cover over platform No.1&2 with seating arrangement, 3- seater benches, coach guidance system etc. provided
5.2. At Ahmadnagar - 6 m wide foot over bridge with escalator provided.
5.3. At Solapur - Provision of passenger amenities & development of circulating areas etc. and 6m wide FOB provided.
5.4. At Daund extension of 6m wide FOB done.
5.5. Prefabricated Divyang toilets provided at 8 stations i.e. SGND, BWD, VPR, SRL, VL, PDGN, CIT, KNGN, YL.
5.6. LUR- Provision of 3.20 Kms D. I. Pipeline from MJP source to Latur Station with
dedicated RCC HS tank and UG sump work completed.
- Photographs of Passenger Amenities - Completed Work in 2020-21. To view, click on the link below:
https://cr.indianrailways.gov.in/uploads/files/1624011807638-SUR Photo 2020-21.pdf