Sr No. | Subject | | |
1 | Time line For Private Sidings Projects | | |
No. | Service | Time limit | Single Window Agency (to be contacted for progress/ non-compliance) |
1.2 | Signing of Siding agreement | 5 days | Sr.DCM of concerned Division |
(working days from the date of completion of work) | Mumbai division |
| srdcm@bb.railnet.gov.in |
| Pune division |
| srdcm@pune.railnet.gov.in |
| Bhusawal division |
| srdcm@bsl.railnet.gov.in |
| Nagpur division |
| srdcm@ngp.railnet.gov.in |
| Solapur division |
| srdcm@ngp.railnet.gov.in |
1.3 | Notification after certification | 05 days | |
(after receipt of completion certificate and signing of Siding Agreement and Land Licensing Agreement | |