SN. | Name of Siding / PFT | Serving Station | Type of Terminal PFT/Pvt. Sdg | Cost of Project (As per DPR) | Target date of commissioning | Remarks |
1 | M/s JNPT Dry Port | Sindi: WR-NGP section– NGP Division | PFT | 29.31cr | March 2022 | The Project was targeted for commissioning in 2019-20 and 2020-21 also but got delayed due to clearance in acquisition of Forest and Private Land. |
2 | RCCPL Private Ltd. | Mukutban (Crossing Station) Wani-Pimpalkutti NGP Divn. | Pvt. Sdg. | 60.82 cr | Dec.2021 | The Project was targeted for commissioning in 2020-21 but was delayed on account of Covid restrictions. |
3 | M/s JSW (Expansion 10 MTPA) | Dolvi (PEN-THAL Section)- BB Divn. | Pvt. Sdg. | 62.28 cr | Dec 2021 | |
4 | M/s Adani Logistics Ltd. (ALL) | Borkhedi (WR-NGP section) – NGP Divn. | PFT | 24.09 cr | March 2022 |
|