| P.H. 11 - New Lines | | |
1. | Chord line at Badnera (MM) | 9.79 | Mar-10 |
| P.H. 14 - Gauge Conversion | | |
2. | Pandharpur -Miraj (137km) | 816.4 | Mar-10 (pending CRS inspection) |
| P.H. 16 - Traffic Facility Works | | |
3. | Mumbai VT-Remodelling of main line complex (Ph-I) | 97.36 | Mar.10 |
4. | Ambernath, Kasara & Thakurli ext. of1 & provn. of7 EMU stabling sidings | 6.2 | Feb.10 |
5. | New Mulund ?Additional Goods shed facilities | 7.64 | Completed |
| P.H. 30 - Road Saftey Works (ROB/RUB) | | |
6. | Jeur-Road Over Bridge (Rly. portion) | 3.64 | Completed |
7. | Nagar Devla-ROB | 2.23 | Mar-09 |
| P.H. 36 - Other Electrical Works | | |
8. | BSL repl of transformers by 21.6 MVA with switchgear | 2.36 | Mar-09 |
| P.H. 42 - Workshops& Sheds | | |
9. | BSL/ ELW-provision of facilities of loco body manipulator. | 1.37 | Aug-09 |
10. | Ghorpuri Yard- Pit lines for maintenance of 24 Coach trains with stabling lines (2nos.) | 7.33 | Aug-09 |
| P.H. 51 - Staff Quarters | | |
11. | Mumbai (Cuffe Parade)-Type-V 12 units | 2.06 | Dec-09 |
12. | Pune ?TransitType IV-24 units | 3.21 | Dec-09 |
13. | PA- Porter chawl - 64 units | 2.17 | Sep-09 |
14. | PA-Portar chawl-RB II 35 units | 1.61 | Nov-09 |
| P.H. 53 - Passenger Amenities | | |
15. | Kalyan-Remodelling & improvement of station | 4.65 | Feb-09 |
| P.H. 81 - MTP Projects | | |
16. | Belapur-PNVL-Doubling of commuterline as part of East-West corridor 10.9Km | 280.31 | Apr-00 |
17. | Thane-Turbhe-Nerul-Vashi-Part of CorridorNo.1 in New Mumbai | 403.39 | Jan-09 |
| MRVC Projects | | |
18. | EMU maintenance facilities - I | 67 | Sep-08 |
19. | Stabling lines - I | 37.57 | Completed |
| DC-AC Conversion Works | | |
20. | Reconstruction of ROB at Dehu Road | 4 | Dec-09 |