About Us
   Construction
      Planning
         Works
            Works Completed During 2008 -09


 
Bookmark Mail this page Print this page
QUICK LINKS
Works Completed During 2008 -09

Sr

No.

Name of work

Cost ofProject

Date of Completion

 

PH 11 - NEW LINES

 

 

 

Puntamba-Shirdi (16.40 km)

78.43

Work completed & commissioned in Feb.09

 

PH-14 Gauge Conversion

 

 

1

Osamanabad-Kurduwadi (72 Kms) Part of Miraj-Latur Gauge Conversion

 

816.40

Completed in March 08 & commissioned in Oct.08

 

PH-15Doubling

 

 

2

Pakni-Mohol 17 Km

47.16

Work completed & commissioned in May 08.

 

PH-33S&T Works

 

 

 

Badnera Replecement ofCentralised gears by centralized operation

5.77

Work completed & commissioned on 17.01.09

3

Repl of signalling gears with centralised operation of points at Nandgaon &Chalisgaon

10.79

Completed.

Chalisgaon -June 08 Nandgaon ? Dec. 07

4

Mumbai div Repl of Centralised gears with Centralized operation (A route) atByculla, Mulund, IGP& Asangaon

14.15

Byculla -May 08 Mulund ?Feb 08

Igatpuri ?Mar. 07 Asangaon ?Nov 05

5

Wardha Repl of Centralised gears by Centralized operation of points & signals

7.58

CompletedApril 08

6

Pune-Repl of signalling gears by centralised operation of points & signalsB route 6 stations

6.03

CompletedApril 08

 

PH-16 Traffic Facilities

 

 

7

Amla- Shifting of operation from A & D Cabin to Central location along with Yard Remodeling.

5.15

Completed Sept.08

8

Badlapur-Karjat Automatic block signaling on suburban section.

17.22

Completed Aug.08

9

Majri-Chord Line connecting Majri Wani branch line with main line.

5.57

Completed in Dec.08

 

PH-42 Workshops

 

 

 

Daund creation of routine over hauling facility

8.34

Work completed in Sept.08

10

Matunga Workshop ? Integrated work station for heavy corrosion repair in shed No.1.

3.05

Work completed Sept.08.

 

BSL Elec loco W/Shop repl.of flooring by Industrial gr.flooring

1.14

Work completed in Oct.08

 

PH 53 ? PASSENGER AMENITIES

 

 

 

Kalyan remodeling & improvement of Stn.building

4.65

Work completed & commissioned on March 09

 

PH-64 Other Specified work

 

 

11

Zonal Training Centre, Bhusawal ? 50 bedded ladies hostel

0.63

Completed Aug08.

 

PH-81 MTP

 

 

12

Thane-Turbhe ? Nerul-Vashi Phase-II Turbhe-Juinagar (4.77km) - Nerul

403.92

Work completed & commissioned in Nov.08.




Source : Central Railway / Indian Railways Portal CMS Team Last Reviewed : 10-02-2011  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.