A. PERFORMANCE OF ELECTRICAL (GENERAL SERVICES) FOR YEAR ENDING 2017-18
SN | Items | Total Cumulative |
1 | Reduction in Non-Traction Energy Consumption | 8.2% |
2 | Tariff Change Benefit a) Old Tariff to New tariff applicable for Rlys. | Rs.4,80,18,635/- |
3 | LED Lights on Stations | 89 Stations completed Expected Saving per Annum Rs. 3,71,52,979 |
4 | LED Lights in Service bldgs | 9 Bldgs. |
5 | LED Lights in HQ & Divisional offices | 7 Bldgs |
6 | Solar Panel | 204.1 Kwp |
7 | Provision of FOB Lifts | 27 Nos. |
9 | Provision of Escalators | 34 Nos. |
10 | Air-conditioning of Running Rooms | 4 |
11 | Air conditioning of TTE Running Rooms | 2 |
12 | 100% Green Energy Stations | 1 Station |
13 | Direct Metering of Staff Quarters | 9196 Nos. |
14 | Rewiring of Staff Quarters | 56 Nos. |
15 | Provision of HVLS Fan | 10 Nos. |
16 | Provision of additional Air Circulators at Stations | 1223 Nos. |